Contract
No: HK/2011/07 Wanchai Development Phase II and Central Wanchai
Bypass Sampling, Field Measurement and
Testing Work (Stage 2) Environmental
Permit no. EP-364/2009/A, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/A and FEP-08/364/2009/A Monthly Environmental
Monitoring & Audit Report
- june 2012 -
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways
Department |
Lam Geotechnics Limited 11/F Centre
Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
                         Raymond Dai Environmental Team Leader |
|
DATE: |
|
11 July 2012 |
1.1    Scope
of the Report
1.2    Structure
of the Report
2.   Project Background
2.1    Background
2.2    Scope
of the Project and Site Description.
2.3    Division
of the Project Responsibility
2.4    Project
Organization and Contact Personnel
3.   status of regulatory compliance
3.1    Status
of Environmental Licensing and Permitting under the Project
4.   Monitoring
Requirements
4.1    Noise
Monitoring
4.2    Air
Monitoring
5.   Monitoring Results
5.1    Noise
Monitoring Results
5.2    Real Time Noise Monitoring Results
5.3    Air
Monitoring Results
5.4    Waste
Monitoring Results
6.1    Noise
Monitoring
6.2    Real Time Noise Monitoring.
6.3    Air
Monitoring
6.4    Review
of the Reasons for and the Implications of Non-compliance
6.5    Summary
of action taken in the event of and follow-up on non-compliance
7.   Cumulative Construction Impact due to the
Concurrent Projects
8.   Environmental Site
Audit
9.   Complaints, Notification of Summons and Prosecution
lIST
OF TABLES
Table 2.1    Schedule 2 Designated Projects under this
Project
Table 2.2   Details of Individual Contracts under the Project
Table 2.3   Contact Details of Key Personnel
Table 3.3   Summary of submission status under FEP-03/364/2009
Table 3.5   Summary of submission status under FEP-02/364/2009
Table 3.7   Summary of submission status under FEP-01/364/2009
Table 3.9   Summary of submission status under FEP-05/364/2009/A
Table 3.10  Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/15
Table 3.11  Summary of submission status under
FEP-06/364/2009/A
Table 3.12  Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/19
Table 3.13  Summary of submission status under
FEP-07/364/2009/A
Table 3.14  Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2010/06
Table 4.1   Noise Monitoring Stations
Table 4.2   Real Time Noise Monitoring Stations
Table 4.3   Air Monitoring Stations
Table 5.1    Noise Monitoring Stations for Contract no. HY/2009/17
Table 5.2    Noise Monitoring Stations for Contract no. HY/2009/18
Table 5.3    Noise Monitoring Station for Contract no HK/2009/01 and
HK/2009/02
Table 5.4    Noise Monitoring Stations for Contract no. HY/2009/15
Table 5.5    Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.6   Real Time Noise Monitoring Stations for Contract no.
HY/2009/17
Table 5.7   Real Time Noise Monitoring Stations for Contract no.
HY/2009/19
Table 5.8    Air Monitoring Station for Contract no. HY/2009/17
Table 5.9    Air Monitoring Stations for Contract no. HY/2009/18
Table 5.10   Air Monitoring Station for Contract no.
HK/2009/01
Table 5.11   Air Monitoring Station for Contract no.
HK/2009/02
Table 5.12   Air Monitoring Station for Contract no. HY/2009/15
Table 5.13   Air Monitoring Stations for Contract no.
HY/2009/19
Table 5.14  Details of Waste Disposal for Contract no.
HY/2009/17
Table 5.15  Details of Waste Disposal for Contract no.
HK/2009/01
Table 5.16  Details of Waste Disposal for Contract no.
HK/2009/02
Table 5.17  Details of Waste Disposal for Contract no.
HY/2009/18
Table 5.18  Details of Waste Disposal for Contract no.
HY/2009/15
Table 5.19  Details of Waste Disposal for Contract no.
HY/2009/19
Table 5.20  Details of Waste Disposal for Contract no. HK/2010/06
Table 8.1   Summary of Environmental Inspections for Contract no.
HY/2009/15
Table 8.2   Summary of Environmental Inspections for Contract no.
HY/2009/19
Table 8.3   Summary of Environmental Inspections for Contract no.
HK/2009/01
Table 8.4    Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.5    Summary of Environmental Inspections for
Contract no. HK/2010/06
Table 9.1   Cumulative Statistics on Complaints
Table 9.2   Cumulative Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure 2.1       Project Layout
Figure
2.2       Project
Organization Chart
Figure 4.1        Locations of
Environmental Monitoring Stations
lIST OF APPENDIces
Appendix
3.1     Environmental Mitigation Implementation Schedule
Appendix 4.1     Action and Limit Level
Appendix 4.2     Copies of Calibration
Certificates
Appendix
5.1     Monitoring Schedule for Reporting Month and Coming month
Appendix
5.2     Noise Monitoring Results and Graphical Presentations
Appendix
5.3     Air Quality Monitoring Results and
Graphical Presentations
Appendix 5.4     Real-time Noise Monitoring
Results and Graphical Presentations
Appendix 6.1     Event Action Plans
Appendix 6.2     Notification of Exceedance
Appendix 9.1     Complaint Log
Appendix 10.1   Construction Programme of
Individual Contracts
i.
This is the
Environmental Monitoring and Audit (EM&A) Monthly Report
 /span> June 2012 specific for Environmental
Permit no. EP-364/2009/A, Further Environmental Permit nos. FEP-01/364/2009,
FEP-02-364/2009, FEP-03-364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A FEP-07/364/2009/A and FEP-08/364/2009/A. The EM&A report is prepared by
the Environmental Team (ET) employed under Contract
No. HK/2011/07  /span> Wan Chai Development Phase II and Central Wanchai Bypass  Sampling, Field Measurement and
Testing Works (Stage 2). This report presents
the environmental monitoring findings and information recorded during the
period May to June 2012. The cut-off
date of reporting is at 27th of each reporting month.
iv.
In the
reporting month, the principal work activities of individual contracts are
included as follows:
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield
Depot - Advanced piling works under FEP-03/364/2009
 -
ELS works for
basement construction for pile cap construction.
Contract no. HY/2009/18 - Central - Wan
Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
 -
Trial Pit
 -
Instrumentation
and monitoring works
 -
Drainage works
 -
Site
investigation and pre-drilling works
 -
D-wall
construction
 -
Sheet piling
 -
Grout curtain
 -
Tree
Transplantation
 -
Earthwork
 -
Preparation
works in existing tunnel
 -
Stitch coring
 -
Approach ramp
structure works
 -
Top down slab
 -
Road works
 -
Tunnel works
 -
Excavation and
Lateral Support
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009
 -
Diaphragm wall
construction works for CWB (Stage2)
 -
Pre-drilling
works for CWB (Stage2)
 -
Pre-bored H
piling works for SCL
 -
Excavation for
CWB top slab (Bay1  Bay 4)
 -
Waterproofing
works for CWB top slab (Bay 1  Bay 4)
 -
Excavation and
installation of shoring system for construction of exhaust duct structure
 -
Excavation for
SCL top slab construction works
 -
Construction
of SCL top slab (Bay 3)
 -
Trimming of
SCL Diaphragm wall head
Contract no.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
 -
Deep
excavation works. The excavation level
has reached -9.0mPD to -9.8mPD on the eastern and western portion of the site respectively.
 -
Tunnel Pre-drill
work of bored pile at tunnel portion 3 & 4 area.
 -
Trench
excavation for guide wall of Diaphragm wall at tunnel portion 3 & 4 area.
 -
Guide wall
construction for Diaphragm wall at tunnel portion 3 & 4 area.
 -
Bored pile
PC34 and PC35.
 -
Pre-drill for
bored pile and diaphragm wall.
 -
Handover of
Government Helipad at Tunnel Portion 3&4 and initial Survey at ex-helipad.
 -
Half bay of
bulkhead wall construction
Contract no. HY/2009/15 -
Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
 -
Diaphragm wall
construction works at TS4
 -
ELS works at
TPCWAE
 -
Cut and cover
tunnel construction at TS1
 -
Night time
protection works at CHT
 -
Cut off wall
preparation works at Hung Hing Road and POC
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
 -
Road works at
Watson Road
 -
Fabrication of
bored piling platform
 -
Bored piling
(Land)
 -
Ground
contamination assessment
 -
Pre-drilling
works for bored pile and Diaphragm wall
 -
D-wall Construction
(North & South Section)
 -
Guide wall
construction for D-wall / Barette at North side
 -
Construction
works for Box Culvert T
 -
Construct ion
of socket-H pile for Marine works
 -
Construction
of pre-bored H-pile works for Culvert U
 -
Installation
of sheet pile at D9 location
 -
Construction
of pile cap
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
 -
Construction
of Pre-cast Unit in China
Noise Monitoring
Monitoring
for report of review baseline noise level was performed from 11 April 2011 to 8
June 2011. Then the report was
submitted on the 20 June 2011, verified by IEC on 18 July 2011 and was approved
by ER by January 2012. The new baseline
is used for the noise calculation of this reporting month starting from January
2012.
viii.
24-hour real time noise
monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitefield
Depot for the pilling works in FEHD Whitfield Depot and RTN2  Tunnel (North
Point Section) and Island Eastern Corridor Link. No project related action
and limit level exceedance was recorded in the reporting period.
Air Monitoring
x.
Due to lack of electricity
supply, the 24-hr TSP monitoring at the following stations were rescheduled
CMA1b: from 6 June 2012 to 7
June 2012
CMA5a: from 6 June 2012 to 7
June 2012
CMA2a: from 18 June 2012 to
19 June 2012
xi.
1-hour and 24-hour Total Suspended
Particulates (TSP) monitoring were conducted at CMA1b - Oil Street Community
Liaison Centre; CMA2a - Causeway Bay Community Center; CMA3a - CWB PRE Site
Office Area; CMA4a  Society for the Prevention of Cruelty to Animals; CMA5a - Children Garden opposite to
Pedestrian Plaza; MA1e and MA1w  International
Finance Centre eastern and western wing on every six days basis. No action and limit level
exceedance were recorded in the reporting period.
Complaints,
Notifications of Summons and Successful Prosecutions
xii.
There was no
environmental complaint received in this
reporting month.
Site Inspections and
Audit
xiii.
The
Environmental Team (ET) conducted weekly site inspections for Contract no.
HY/2009/15, HY/2009/17, HY/2009/18, HY/2009/19, HK/2009/01, HK/2009/02 and
HK/2010/06 in this reporting period. The Contractors rectified major
observations and recommendations made during the audit sessions. No
non-conformance was identified during the site inspections.
xiv.
In the coming
reporting month, the principal work activities of individual contracts are
anticipated as follows:
Contract no. HY/2009/17  Central  Wan
Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under
FEP-03/364/2009
 -
ELS works for
basement construction for pile cap construction.
Contract no. HY/2009/18  Central  Wan
Chai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A
 -
Trial pit
 -
Instrumentation
and monitoring works
 -
Drainage works
 -
Site
investigation and pre-drilling works
 -
D-wall
construction
 -
Sheet piling
 -
Tree
Transplantation
 -
Earthworks
 -
Preparation
works in existing tunnel
 -
Approach ramp
(trough) structure works
 -
Top down slab
 -
Road works
 -
Tunnel works
 -
Excavation and
Lateral Support
 -
Pipe-pile
works
 -
Cooling main
bridge construction
 -
Bridge A
construction
Contract no.
HK/2009/01  Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre  Tunnel Works under FEP-02/364/2009
 -
Diaphragm wall
construction for CWB tunneling works at Stage2
 -
Waterproofing
works for CWB top slab
 -
Excavation and
installation of shoring system for construction of exhaust dust
 -
Construction
of exhaust duct structure (Bay1)
 -
Construction
of exhaust duct structure (Bay2)
 -
Load test on
SCL pre-bored H-piles works
 -
Excavation for
construction of SCL top slab
 -
Construction
of SCL top slab (Bay 3)
 -
Construction
of SCL top slab (Bay1 and Bay 2)
Contract no.
HK/2009/02  Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
 -
Bored piling,
breaking concrete slab and excavation of trial pit at tunnel portion 3 & 4.
 -
Deep
excavation and strut installation works below -9.8mPD for western tunnel
portion and below +9.0mPD for eastern tunnel portion.
Contract no. HY/2009/15  
Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
 -
Diaphragm wall
construction works at TS4
 -
ELS works at
TPCWAE
 -
Cut and cover
tunnel construction at TPCWAE
 -
Mined tunnel
preparation works at TPCWAE and Hung Hing Road
Contract no. HY/2009/19  Central  
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
 -
Road works at
Watson Road
 -
Laying od 1500f drainage pipe
 -
Fabrication of
bored piling platform
 -
Bored piling
(Land)
 -
Ground
contamination assessment
 -
Pre-drilling
works for bored pile and Diaphragm wall
 -
D-wall Construction
(North & South Section)
 -
Guide wall
construction for D-wall / Barette at North side
 -
Construction
works for Box Culvert T
 -
Construct ion
of socket-H pile for Marine works
 -
Construction
of pre-bored H-pile works for Culvert U
 -
Construction
of 1500 drainage along D-wall
 -
Construction
of pile cap
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
 -
Construction
of Pre-cast Unit in China
1.1.1.
Lam Geotechnics Limited (LGL) has been
appointed to work as the Environmental Team (ET) under Environmental Permit no.
EP-364/2009A and Further Environmental permit nos.
FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A and FEP-08/364/2009/A to implement the
Environmental Monitoring and Audit (EM&A) programme as stipulated in the
EM&A Manual of the approved Environmental Impact Assessment (EIA) Report
for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This report presents the environmental
monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and  /span>Environmental Monitoring and Audit Requirements /span> under Particular
Specification Section 27.
1.1.3.
This report
documents the finding of EM&A works for Environmental Permit (EP) no.
EP-364/2009/A, Further Environmental Permit (FEP) nos. FEP-01-364/2009,
FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A,
FEP-07/364/2009/A and FEP-08/364/2009/A during the period May to June 2012. The cut-off date of reporting is at 27th of each reporting
month.
Section 1     Introduction  details
the scope and structure of the report.
Section 2     Project
Background  summarizes background and scope of the project, site
description, project organization and contact details of key personnel during
the reporting period.
Section 3     Status of Regulatory Compliance  
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section 4     Monitoring
Requirements  summarizes all monitoring parameters, monitoring
methodology and equipment, monitoring locations, monitoring frequency, criteria
and respective event and action plan and monitoring programmes.
Section 5     Monitoring
Results  summarizes the monitoring results obtained in the
reporting period.
Section 6     Compliance Audit  
summarizes the auditing
of monitoring results, all exceedances environmental parameters.
Section 7     Cumulative Construction Impact due to the Concurrent Projects  summarizes the relevant cumulative construction impact due to the
concurrent activities of the concurrent Projects.
Section 8     Site Inspection  summarizes the findings of
weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.
Section 9     Complaints, Notification of summons and Prosecution  
summarizes the cumulative statistics on
complaints, notification of summons and prosecution
Section 10    Conclusion
2.1.1.
“Wan Chai Development phase II and
Central-Wan Chai Bypass and “Central-Wan Chai Bypass and Island Eastern
Corridor Link (hereafter called “the Project  are Designated Project (DP) under the Environmental Impact Assessment
Ordinance (Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai
Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008)
have been approved on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development
Phase II (WDII) is to provide land at Wan Chai North and North Point for
construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link
(CWB). Land formed under the project will be developed as a world-class
waterfront promenade joining that at the new Central waterfront for public
enjoyment.
2.1.3.
There is a compelling and present need
for the CWB to provide relief to the very congested east-west Connaught Road
Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is
currently operating beyond its capacity. The CWB will provide relief to the
existing congestion along the Corridor and cater for the anticipated growth of
traffic on Hong Kong Island. Without the CWB and its access roads, there will
not be sufficient capacity to serve the heavy traffic demands at both strategic
and local levels.
2.2.1.
Design and
Construction of Central  Wan Chai Bypass and Island Eastern Corridor Link
under the Project involves the construction and operation of a trunk road and
its road tunnel more than 800m in length between portals that is shown at Figure 2.1.
2.2.2.
The study area
encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
 -
A dual
three-lane trunk road, approximately 4.5 km in length, and tunnel approximately
3.7 km in length defined from the connection with the existing Rumsey Street
Flyover in Central, through to a connection with the existing Island Eastern
Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
 -
The Central
Interchange near the Rumsey Street Flyover to provide road connections to the
Central area;
 -
Tunnel control
buildings and ventilation buildings;
 -
Slip roads to
connect the CWB to the local road system in the Wan Chai North and Causeway Bay
area;
 -
Associated
road lighting, road signing, traffic control and surveillance system; and
 -
Other
associated works.
2.2.3.
The project also contains various
Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the
five individual DPs under this Project. Figure 2.1 shows the locations
of these Schedule 2 DPs.
Table
2.1   Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the
Project, there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced. 
Contractors of individual contracts will be required by the EP holder to
apply Further Environmental Permits such that the impact
monitoring stations are sub-divided accordingly to facilitate the
implementation of EM&A programme and to streamline the EM&A reporting
for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are
summarized in Table2.2.
Table
2.2  Details of Individual Contracts
under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central  Wan Chai Bypass (CWB)  Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong Kong
Convention and Exhibition Centre  Tunnel Works |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) |
DP1 |
13 July 2011 |
HY/2009/19 |
Central  Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
2.4.1.
Civil
Engineering and Development Department and Highways Department are the overall
project controllers for the Wan Chai Development Phase II and Central-Wan Chai
Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and
lines of communication with respect to environmental protection works are shown
in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3  Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3922 8332 |
3529 2829 |
|
Lam Woo & CO., LTD. |
Contractor under Contract no. HY/2009/17 |
Project Manager |
Mr. K. S. Law |
9090 1378 |
2566 7522 |
Site Agent |
Mr. Tony Au |
9725 5874 |
2566 7522 |
||
Sub Agent |
Mr. Johnny Wong |
9725 5870 |
2566 7522 |
||
Chun Wo  Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint Venture Board Representative |
Mr. PL Yue |
2162 9909 |
2634 1626 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Sub Agent |
Mr. Terry Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack Chu |
9775 2467 |
|||
Construction
Manager |
Mr KK Yuen |
9498 1213 |
|||
Construction
Manager |
Mr. Andy Yu |
9648 4896 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Environmental
Supervisor |
Ms. Kiwi Chan |
6227 8840 |
|||
|
|
Environmental
Supervisor |
Mr. Yeung Sze King |
9047 9952 |
|
Environmental
Supervisor |
Mr. Les Chow |
6692 2423 |
|
||
Chun Wo  CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. Chan Sing Cho |
3658-3002 |
2827 9996 |
Quality & Environmental Manager |
Mr. C.P. Ho |
3658-3000 |
|||
Environmental Officer |
Ms Flora Ng |
3658-3064 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Assistant Site Agent |
Mr. Eric Fong |
6191 9337 |
|||
Environmental Engineer |
Mr. Simon Wong |
9281 4346 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Brian Gillon |
2214 7700 |
|
Deputy Site Agent |
Mr. Desmond Sze |
2214 7703 |
|||
Environmental Officer |
Mr. Anfernee Chow |
2214 7721 |
|||
Environmental Supervisor |
K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Ray Cheng |
2214 7742 |
|||
Environmental Supervisor |
K. W. Lee |
6461 4623 |
|||
|
|
Environmental Supervisor |
Ryan Tsui |
2214 7705 |
|
|
|
Environmental Supervisor |
Bosco Lee |
2214 7711 |
|
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
Chan Wai Hung |
2823 7813 |
2865 5229 |
Site Manager |
Mr. P.J. Fan |
3557 6368 |
2566 2192 |
||
Contractor’s Representative |
Mr. David Lau |
3557 6358 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|||
Environmental Supervisor |
Mr. Kelven Yip |
3557 6347 |
|||
Environmental Supervisor |
Mr. Tim Fung |
3557 6349 |
|||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Lee Wai Man |
9481 6024 |
|||
Environmental
Supervisor |
Mr. Clement
Pang |
9735 9200 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team
Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
In this
reporting month, the principal work activities of individual contracts are
included as follows:
Contract no. HY/2009/17  Central  Wan
Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under
FEP-03/364/2009
 -
ELS works for
basement construction for pile cap construction.
Contract no. HY/2009/18  Central  Wan Chai Bypass (CWB)  Central
Interchange under FEP-05/364/2009/A
 -
Trial Pit
 -
Instrumentation
and monitoring works
 -
Drainage works
 -
Site
investigation and pre-drilling works
 -
D-wall
construction
 -
Sheet piling
 -
Grout curtain
 -
Tree
Transplantation
 -
Earthwork
 -
Preparation
works in existing tunnel
 -
Stitch coring
 -
Approach ramp
structure works
 -
Top down slab
 -
Road works
 -
Tunnel works
 -
Excavation and
Lateral Support
Contract no. HK/2009/01  Wan Chai Development
Phase II  Central  Wan Chai Bypass at Hong Kong Convention and Exhibition Centre
 Tunnel Works under FEP-02/364/2009
 -
Diaphragm wall
construction works for CWB (Stage2)
 -
Pre-drilling
works for CWB (Stage2)
 -
Pre-bored H
piling works for SCL
 -
Excavation for
CWB top slab (Bay1  Bay 4)
 -
Waterproofing
works for CWB top slab (Bay 1  Bay 4)
 -
Excavation and
installation of shoring system for construction of exhaust duct structure
 -
Excavation for
SCL top slab construction works
 -
Construction
of SCL top slab (Bay 3)
 -
Trimming of
SCL Diaphragm wall head
Contract no. HK/2009/02  Wan Chai Development
Phase II  Central  Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
 -
Deep
excavation works. The excavation level
has reached -9.0mPD to -9.8mPD on the eastern and western portion of the site respectively.
 -
Tunnel Pre-drill
work of bored pile at tunnel portion 3 & 4 area.
 -
Trench
excavation for guide wall of Diaphragm wall at tunnel portion 3 & 4 area.
 -
Guide wall
construction for Diaphragm wall at tunnel portion 3 & 4 area.
 -
Bored pile
PC34 and PC35.
 -
Pre-drill for
bored pile and diaphragm wall.
 -
Handover of
Government Helipad at Tunnel Portion 3&4 and initial Survey at ex-helipad.
 -
Half bay of
bulkhead wall construction
Contract no. HY/2009/15  Central-Wanchai Bypass  Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
 -
Diaphragm wall
construction works at TS4
 -
ELS works at
TPCWAE
 -
Cut and cover
tunnel construction at TS1
 -
Night time
protection works at CHT
 -
Cut off wall
preparation works at Hung Hing Road and POC
Contract no. HY/2009/19  Central  Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
 -
Road works at
Watson Road
 -
Fabrication of
bored piling platform
 -
Bored piling
(Land)
 -
Ground
contamination assessment
 -
Pre-drilling
works for bored pile and Diaphragm wall
 -
D-wall Construction
(North & South Section)
 -
Guide wall
construction for D-wall / Barette at North side
 -
Construction
works for Box Culvert T
 -
Construct ion
of socket-H pile for Marine works
 -
Construction
of pre-bored H-pile works for Culvert U
 -
Installation
of sheet pile at D9 location
 -
Construction
of pile cap
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
 -
Construction
of Pre-cast Unit in China
2.4.4.
In coming reporting month, the principal
work activities of individual contracts are anticipated as follows:
Contract no.
HY/2009/17  Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced
piling works under FEP-03/364/2009
 -
ELS works for
basement construction for pile cap construction.
Contract no. HY/2009/18  Central  Wan Chai Bypass (CWB)  Central
Interchange under FEP-05/364/2009/A
 -
Trial pit
 -
Instrumentation
and monitoring works
 -
Drainage works
 -
Site
investigation and pre-drilling works
 -
D-wall
construction
 -
Sheet piling
 -
Tree
Transplantation
 -
Earthworks
 -
Preparation
works in existing tunnel
 -
Approach ramp
(trough) structure works
 -
Top down slab
 -
Road works
 -
Tunnel works
 -
Excavation and
Lateral Support
 -
Pipe-pile
works
 -
Cooling main
bridge construction
 -
Bridge A
construction
Contract no.
HK/2009/01  Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre  Tunnel Works under FEP-02/364/2009
 -
Diaphragm wall
construction for CWB tunneling works at Stage2
 -
Waterproofing
works for CWB top slab
 -
Excavation and
installation of shoring system for construction of exhaust dust
 -
Construction
of exhaust duct structure (Bay1)
 -
Construction
of exhaust duct structure (Bay2)
 -
Load test on
SCL pre-bored H-piles works
 -
Excavation for
construction of SCL top slab
 -
Construction
of SCL top slab (Bay 3)
 -
Construction
of SCL top slab (Bay1 and Bay 2)
Contract no.
HK/2009/02  Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
 -
Bored piling,
breaking concrete slab and excavation of trial pit at tunnel portion 3 & 4.
 -
Deep
excavation and strut installation works below -9.8mPD for western tunnel
portion and below +9.0mPD for eastern tunnel portion.
Contract no. HY/2009/15  
Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
 -
Diaphragm wall
construction works at TS4
 -
ELS works at
TPCWAE
 -
Cut and cover
tunnel construction at TPCWAE
 -
Mined tunnel
preparation works at TPCWAE and Hung Hing Road
Contract no. HY/2009/19  Central  
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
 -
Road works at
Watson Road
 -
Laying od 1500f drainage pipe
 -
Fabrication of
bored piling platform
 -
Bored piling
(Land)
 -
Ground
contamination assessment
 -
Pre-drilling
works for bored pile and Diaphragm wall
 -
D-wall Construction
(North & South Section)
 -
Guide wall
construction for D-wall / Barette at North side
 -
Construction
works for Box Culvert T
 -
Construct ion
of socket-H pile for Marine works
 -
Construction
of pre-bored H-pile works for Culvert U
 -
Construction
of 1500 drainage along D-wall
 -
Construction
of pile cap
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
 -
Construction
of Pre-cast Unit in China
3.1.1.
A summary of the current status on
licences and/or permits on environmental protection pertinent to the Project is
shown in Table 3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
 4 Aug 2010 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental
Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Valid |
Further Environmental
Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further Environmental
Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Valid |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Valid |
|
Further Environmental Permit |
15 June 2012 |
Valid |
3.1.2.
Contract no.
HK/2010/06, Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR
Tsuen Wan Line, has submitted an application for Further Environmental Permit
under EP-364/2009/A on 21 May 2012 and received Further Environmental Permit  
FEP-08/364/2009/A on 15 June 2012.
3.1.3.
Due to the multi-contract nature of the
Project, the status of permits and/or licences under the individual contract(s)
are presented as below:
Contract no. HY/2009/17  Central  Wan
Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under
FEP-03/364/2009
3.1.4.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under FEP-03/364/2009 for contract no. HY/2009/17 showed in Table
3.2 and Table 3.3.
Table 3.2  Cumulative
Summary of Valid Licences and Permits under Contract no.
HY/2009/17
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
N/A |
Valid |
Notification of Works Under APCO |
319348 |
13 Jul 2010 |
N/A |
Valid |
Discharge Licence |
WT00007212-2010 |
5 Aug 2010 |
5 Aug 2010  31 Aug 2015 |
Valid |
Registration as a Waste Producer |
5213-151-L2608-05 |
13 July 2010 |
N/A |
Valid |
Billing Account
under Waste Disposal Ordinance |
7010400 |
16 Mar 2010 |
N/A |
Valid |
Table 3.3  Summary of submission status under FEP-03/364/2009
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
18 September 2010 |
Conditions 2.7 and
2.8 |
Submission of works schedule and location plan |
1 September 2010 |
Condition 2.9 |
Noise Management Plan |
1 September 2010 |
Contract no. 04/HY/2006  /span> Reconstruction of Bus Terminus near
Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
3.1.5.
The
construction works was completed, and the FEP was surrendered by the Contractor
on 11 February 2011.
Contract no.
HK/2009/01  Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre  Tunnel Works under FEP-02/364/2009
3.1.6.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table
3.4 and Table 3.5
Table 3.4  Cumulative Summary of
Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of
Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for non-piling equipment |
GW-RS1221-11 |
30 Dec 2011 |
20 Jan 2012 to 19 Jul 2012 |
Valid |
|
GW-RS1227-11 |
30 Dec 2011 |
30 Dec 2011 to 26 Jul 2012 |
Cancelled |
|
GW-RS0038-12 |
16 Jan 2012 |
15 Jan 2012 to 12 Jul 2012 |
Cancelled |
|
GW-RS0158-12 |
24 Feb 2012 |
24 Feb 2012 to 23 Aug 2012 |
Valid |
|
GW-RS0181-12 |
24 Feb 2012 |
27 Feb 2012 to 23 Aug 2012 |
Valid |
|
GW-RS0213-12 |
28 Feb 2012 |
29 Feb 2012 to 27 Aug 2012 |
Valid |
|
GW-RS0225-12 |
02 Mar 2012 |
14 Mar 2011 to 13 Sep 2012 |
Valid |
|
GW-RS0227-12 |
02 Mar 2012 |
16 Mar 2011 to 15 Sep 2012 |
Valid |
|
GW-RE0174-12 |
05 Mar 2012 |
30 Mar 2012 to  /span>29 Sep
2012 |
Valid |
|
GW-RS0312-12 |
28 Mar 2012 |
30 Mar 2012 to  /span>29 Sep 2012 |
Valid |
|
GW-RS0314-12 |
29 Mar 2012 |
30 Mar 2012 to 25
Sep 2012 |
Cancelled |
|
GW-RS0356-12 |
03 Apr 2012 |
11 Apr 2012  to 29 Sep 2012 |
Valid |
|
GW-RS0394-12 |
16 Apr 2012 |
19 Apr 2012  to 12 Oct 2012 |
Valid |
|
GW-RS0459-12 |
3 May 2012 |
7 May 2012 to  /span>6 Nov 2012 |
Cancelled |
|
GW-RS0460-12 |
10 May 2012 |
13 May 2012 to 6
Nov 2012 |
Valid |
|
GW-RS0492-12 |
14 May 2012 |
15 May 2012 to 3
June 2012 |
Valid |
|
GW-RS0514-12 |
14 May 2012 |
27 May 2012 to 26
Nov 2012 |
Valid |
|
GW-RS0545-12 |
24 May 2012 |
26 May 2012 to 25
Nov 2012 |
Valid |
|
GW-RS0546-12 |
25 May 2012 |
26 May 2012 to 25
Nov 2012 |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
|
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
Billing account under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table 3.5  Summary of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May 2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
18 May 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
25 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
10 Jun 2011 |
Contract no.
HK/2009/02  Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
3.1.7.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table
3.6 and Table 3.7.
Table 3.6  Cumulative Summary of
Valid Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS1028-11 |
3 Nov 2011 |
7 Dec 2011 to 6 June 2012 |
Valid (Expired on 6 June 2012) |
|
GW-RS1111-11 |
28 Nov 2011 |
29 Nov 2011 to 28 May 2012 |
Expired |
|
GW-RS1116-11 |
28 Nov 2011 |
13 Dec 2011 to 12 June 2012 |
Valid (Expired on 12 June 2012) |
|
GW-RS1209-11 |
3 Jan 2012 |
17 Jan 2012 to 16 July 2012 |
Valid |
|
GW-RS0037-12 |
19 Jan 2012 |
1 Feb 2012 to 31 July 2012 |
Valid |
|
GW-RS0051-12 |
19 Jan 2012 |
1 Feb 2012 to 31 July 2012 |
Valid |
|
GW-RS0086-12 |
30 Jan 2012 |
3 Feb 2012 to 2 Aug 2012 |
Cancelled |
|
GW-RS0105-12 |
3 Feb 2012 |
10 Feb 2012 to 9 Aug 2012 |
Valid |
|
GW-RS0153-12 |
17 Feb 2012 |
21 Feb 2012 to 20 Aug 2012 |
Valid |
|
GW-RS0233-12 |
6 Mar 2012 |
9 Mar 2012 to 8 Sept 2012 |
Cancelled |
|
GW-RS0255-12 |
14 Mar 2012 |
17 Mar 2012 to 15 Sept 2012 |
Valid |
|
GW-RE0283-12 |
5 Apr 2012 |
1 May 2012 to 30 Nov 2012 |
Valid |
|
GW-RS0298-12 |
22 Mar 2012 |
26 Mar 2012 to 25 June 2012 |
Valid (Expired on 25 June 2012) |
|
GW-RS0301-12 |
20 Mar 2012 |
21 Mar 2012 to 20 Sept 2012 |
Valid |
|
GW-RS0303-12 |
26 Mar 2012 |
27 Mar 2012 to 27 Sept 2012 |
Valid |
|
GW-RS0341-12 |
3 Apr 2012 |
28 Apr 2012 to 27 Oct 2012 |
Valid |
|
GW-RS0348-12 |
3 Apr 2012 |
10 Apr 2012 to 9 Oct 2012 |
Valid |
|
GW-RS0380-12 |
12 Apr 2012 |
1 May 2012 to 31 Oct 2012 |
Valid |
|
GW-RS0388-12 |
13 Apr 2012 |
1 May 2012 to 31 Oct 2012 |
Valid |
|
GW-RS0418-12 |
30 Apr 2012 |
23 May 2012 to 22 Nov 2012 |
Valid |
|
GW-RS0420-12 |
30 Apr 2012 |
18 May 2012 to 17 Nov 2012 |
Valid |
|
GW-RS0423-12 |
30 Apr 2012 |
19 May 2012 to 18 Nov 2012 |
Valid |
|
GW-RS0427-12 |
30 Apr 2012 |
23 May 2012 to 22 Nov 2012 |
Valid |
|
GW-RS0445-12 |
30 Apr 2012 |
1 May 2012 to 25 Sept 2012 |
Valid |
|
GW-RS0467-12 |
10 May 2012 |
14 May 2012 to 10 Nov 2012 |
Valid |
|
GW-RS0533-12 |
21 May 2012 |
21 May 2012 to 10 Nov 2012 |
Valid |
|
GW-RS0550-12 |
25 May 2012 |
7 June 2012 to 6 Dec 2012 |
Valid |
|
GW-RS0611-12 |
14 June 2012 |
15 Jun 2012 to 28 Nov 2012 |
Valid |
|
GW-RS0633-12 |
13 June 2012 |
16 Jun 2012 to 14 Dec 2012 |
Valid |
Construction Noise Permit (CNP) for piling equipment |
PP-RS0007-12 |
27 Mar 2012 |
28 Mar 2012 to 27 Sept 2012 |
Valid |
Discharge Licence |
WT00006249-2010 |
22 Mar 2010 |
31 Mar 2015 |
Valid |
|
WT00006436-2010 |
15 Apr 2010 |
30 Apr 2015 |
Valid |
|
WT00006673-2010 |
14 May 2010 |
31 Mar 2015 |
Valid |
|
WT00006757-2010 |
28 May 2010 |
31 May 2015 |
Valid |
|
WT00007129-2010 |
28 July 2010 |
31 Jul 2015 |
Valid |
|
WT00008982-2011 |
26 April 2011 |
30 April 2016 |
Valid |
|
WT00009691-2011 |
1 Aug 2011 |
31 July 2016 |
Valid |
Billing Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Table 3.7  Summary of submission
status under FEP-01/364/2009
EP Condition |
Submission |
Date of Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
14 Jun 2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
14 Jun 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
21 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan (Revision A) |
13 Jan 2012 |
Condition 2.11 |
Landscape Plan
(Revision B) |
21 Feb 2012 |
Condition 2.9 |
Noise Management Plan
(Rev.A) |
13 Jan 2012 |
Contract no. HY/2009/18  Central  Wan Chai Bypass
(CWB)  Central Interchange under FEP-05/364/2009/A
3.1.8.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.8
and Table 3.9.
Table 3.8  Cumulative Summary of
Valid Licences and Permits under Contract no. HY/2009/18
Permit / Licence / Notification /
Approval |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Permit issued |
Valid |
Notification of Works Under APCO |
322293 |
07 Oct 2010 |
Notified |
Valid |
Construction Noise Permit (CNP) for non-piling
equipment |
GW-RS0261-12 |
09 Mar 2012 |
10 Mar 2012  br>
09 Sep 2012 |
Valid |
Discharge Licence |
WT00008229-2011 |
13 Jan 2011 |
25 May 2012 |
Expired |
WT00012998-2012 |
25 May 2012 |
31 Jan 2016 |
Valid |
|
Registration as a
Waste Producer |
WPN:
8335-121-L1048-04 |
17 Dec 2010 |
N/A |
Registration
completed |
Billing Account
under Waste Disposal Ordinance (Land) |
Account No.:
7011587 |
11 Oct 2010 |
Account approved |
Valid |
Table 3.9  Summary of submission
status under FEP-05/364/2009/A
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management
Plan |
01 March 2011 |
Condition 2.10 |
Landscape Plan
(Rev. 5) |
12 March 2012 |
Contract no. HY/2009/15  Central-Wanchai
Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
3.1.9.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table
3.10 and Table 3.11
Table
3.10 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental
Permit |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
|
Notification of Works
Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for non-piling equipment |
GW-RS1211-11 |
22 Dec 2011 |
24 Dec 2011 to 21 Jun 2012 |
Valid (Expired on 21 Jun 2012) |
|
GW-RS1149-11 |
7 Dec 2011 |
8 Dec 2011 to 7 Jun 2012 |
Cancelled |
|
GW-RS0150-12 |
22 Feb 2012 |
27 Feb 2012 to 24 Aug 2012 |
Cancelled |
|
GW-RS0094-12 |
1 Feb 2012 |
3 Feb 2012 to 31 Jul 2012 |
Valid |
|
GW-RS0330-12 |
29 Mar 2012 |
3 Apr 2012 to 21 Sep 2012 |
Cancelled |
|
GW-RS0328-12 |
30 Mar 2012 |
1 Apr 2012 to 22 Sep 2012 |
Valid |
|
GW-RS0190-12 |
28 Feb 2012 |
28 Feb 2012 to 11 Aug 2012 |
Cancelled |
|
GW-RS0249-12 |
10 Feb 2012 |
9 Mar 2012
to 31 Aug 2012 |
Valid |
|
GW-RS0552-12 |
24 May 2012 |
25 May 2012
to 20 Oct 2012 |
Cancelled |
|
GW-RS0586-12 |
4 Jun 2012 |
5 Jun 2012 to 30 Sep 2012 |
Valid |
|
GW-RS0695-12 |
24 Jun 2011 |
25 Jun 2012 to 21 Dec 2012 |
Valid |
|
GW-RS0700-12 |
26 Jun 2012 |
26 Jun 2012 to 25 Dec 2012 |
Valid |
|
GW-RS0607-12 |
12 Jun 2012 |
13 Jun 2012 to 7 Dec 2012 |
Valid |
Registration
as a Chemical Waste Producer |
WPN:
5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under
Waste Disposal Ordinance |
7011553 |
30 Sep 2010 |
27 Sep 2010 to 27 Jan 2016 |
Valid |
Water
Discharge License (Discharge at TS1) |
WT00008780-2011 |
24 Nov 2011 |
24 Nov 2011
to 31 Mar 2016 |
Valid |
Water
Discharge License (Discharge at Hung
Hing Road) |
WT00010482-2011 |
30 Sep 2011 |
30 Sep 2011
to 30 Sep 2013 |
Cancelled |
Water
Discharge License (Discharge at CHT
area) |
WT00012941-2012 |
10 May 2012 |
10 May 2012
to 31 May 2014 |
Valid |
Water Discharge
License (Discharge at TPCWAE) |
WT00011322-2011 |
15 Dec 2011 |
15 Dec 2011
to 31 Dec 2013 |
Valid |
Water
Discharge License (Discharge at TS4) |
WT00011718-2012 |
16 Jan 2012 |
16 Jan 2012
to 31 Jan 2014 |
Valid |
Table 3.11 Summary of submission
status under FEP-06/364/2009/A
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
11 Mar 2011 |
Amendment for Management Organization of Main Construction Companies |
16 May 2011 |
|
Condition 2.7 |
Works Schedule |
15 Mar 2011 |
Condition 2.8 |
Location Plan |
15 Mar 2011 |
Condition 2.23 |
Noise Management Plan |
6 May 2011 |
Contract no. HY/2009/19  Central  
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
3.1.10.
The current status on licences and/or permits on environmental
protection pertinent and submission under FEP-07/364/2009/A for contract no. HY/2009/19 are shown in Table
3.12 and Table 3.13.
Table 3.12 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/19
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental
Permit |
25 Feb 2011 |
N/A |
Valid |
|
Notification of Works
Under APCO |
326160 |
24 Jan 2011 |
N/A |
Valid |
Registration as a Waste
Producer |
7012306 |
10 Feb 2011 |
N/A |
Valid |
Registration as
Chemical Waste Producer |
5213-151-C3654-01 |
24 Mar 2011 |
N/A |
Valid |
Application for Vessel
Disposal |
7012306 |
21 July 2011 |
N/A |
Valid |
Construction Noise
Permit (CNP) |
GW-RS0180-12 |
22-Feb-12 (Effective 27-Feb-12) |
26-Aug-12 |
Valid |
|
GW-RS0507-12 |
22-May-12 (Effective 24-May-12) |
23-Nov-12 |
Valid |
|
GW-RS0028-12 |
18-Jun-12 |
17-Dec-12 |
Valid |
|
GW-RS0286-12 |
23-Mar-12 (Effective 27-Mar-12) |
26-Sep-12 |
Cancelled |
Water Discharge Licence |
WT00010093-2011 |
31-Aug-11 |
30-Sep-16 |
Valid |
|
WT00010865-2011 |
3-Nov-11 |
30-Nov-16 |
Valid |
Table 3.13 Summary of submission
status under FEP-07/364/2009/A
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management Plan |
02 Jun 2011 |
Condition
2.13 |
Landscape
Plan |
16 March 2012 |
Condition 2.9 |
Noise Management Plan(Rev.2) |
28-Oct-11 |
3.1.11. Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under FEP-08/364/2009/A for contract no. HK/2010/06 showed in Table
3.14 and Table 3.15.
Table 3.14 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2010/06
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-08/364/2009/A |
15 June 2012 |
N/A |
Valid |
Notification of Works Under APCO |
326344 |
18 Jan 2011 |
N/A |
Valid |
No submission has been made under
FEP-08/364/2009/A in this reporting month.
Noise Monitoring Stations
4.1.1.
The noise monitoring stations for the
Project are listed and shown in Table 4.1 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.1  Noise Monitoring
Stations
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire
Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church
Henrietta Secondary School |
M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
Real time Noise Monitoring Stations
4.1.2.
Review of
feasibility on the real time noise monitoring stations was conducted in July
with IEC. Station, RTN1a, Tung Lo Wan fireboat Station was found not
appropriate to be a monitoring station for monitoring the IECL Piling works and
Demolition after visited. 
4.1.3.
Reviewing the
works schedule of HY/2009/19, IECL Bridge Demolition from City Garden to
Provident Garden will commence in July 2012. 
“Proposal on The Real Time Noise Monitoring System at RTN3 was
submitted and verified by IEC on .
4.1.4.
The noise monitoring stations for the
Project are listed and shown in Table 4.2
and Figure 4.1.. Appendix 4.1
shows the established Action/Limit Levels for the monitoring works.
Table 4.2  Real Time Noise Monitoring Stations
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
Noise Monitoring
Parameters, Frequency and Duration
4.1.5.
The construction noise level shall be measured in
terms of the A-weighted equivalent continuous
sound pressure level (Leq). Leq (30 minutes)
shall be used as the monitoring parameter for the time period between 0700 and 1900 hours
on normal weekdays. For all other time periods, Leq (5 minutes)
shall be employed for comparison with the Noise Control Ordinance (NCO)
criteria. Supplementary information for
data auditing, statistical results such as L10 and L90
shall also be obtained for reference.
4.1.6.
Noise monitoring shall be carried
out at all the designated monitoring stations. The monitoring frequency shall
depend on the scale of the construction activities. The following is an initial
guide on the regular monitoring frequency for each station on a weekly basis
when noise generating activities are underway:
 -
One set of measurements between
0700 and 1900 hours on normal weekdays.
4.1.7.
Real time noise shall be carried
out at the designated monitoring stations. The following is an initial guide on
the regular monitoring frequency for each station on a 24 hours daily basis
when noise generating activities are underway:
 -
One set of measurements between
0700 and 1900 hours on normal weekdays.
 -
One set of measurements between
1900 and 2300 hours on normal weekdays and 0700 and 2300 hours on public
holidays.
 -
One set of measurements between
2300 and 0700 hours on next day on everyday.
4.1.8.
If construction works are
extended to include works during the hours of 1900  0700 as well as public
holidays and Sundays, additional weekly impact monitoring shall be carried out
during respective restricted hours periods. Applicable permits under NCO shall
be obtained by the Contractor.
Monitoring Equipment
4.1.9.
As referred to in the Technical
Memorandum  issued under the NCO, sound level meters in compliance with the
International Electrotechnical Commission Publications 651: 1979 (Type 1) and
804: 1985 (Type 1) specifications shall be used for carrying out the noise
monitoring. Immediately prior to and following each noise measurement the
accuracy of the sound level meter shall be checked using an acoustic calibrator
generating a known sound pressure level at a known frequency. Measurements may
be accepted as valid only if the calibration level from before and after the
noise measurement agree to within 1.0 dB.
4.1.10. Noise measurements shall not be made in fog, rain, wind with a steady
speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall
be checked with a portable wind speed meter capable of measuring the wind speed
in m/s.
4.1.11. The sound level meter shall be checked using an acoustic calibrator
generating a known sound pressure level at a known frequency before deployment
to the site and during each site visit. Measurements will be accepted as valid
only if the calibration level from before and after the noise measurement agree
to within 1.0 dB.
Air Quality Monitoring
Stations
4.2.1.
The air monitoring stations for
the Project are listed and shown in Table 4.3 and Figure 4.1.. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.3  Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil
Street Community Liaison Centre |
North Point (Re-commenced on 14 November 2011) |
CMA2a |
Causeway Bay Community
Centre |
Causeway Bay |
CMA3a |
CWB PRE Site Office * |
Causeway Bay |
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Garden opposite to Pedestrian Plaza |
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (western End of Podium) |
Central |
Remarks: As per
the ENPC meeting in March 2011, the monitoring stations CMA3a  Future CWB site
office at Wanchai Waterfront Promenade was renamed as remark.
Air Monitoring Parameters,
Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels
should be measured to indicate the impacts of construction dust on air quality.
The 24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
4.2.3.
All relevant data including
temperature, pressure, weather conditions, elapsed-time meter reading for the
start and stop of the sampler, identification and weight of the filter paper,
and any other local atmospheric factors affecting or affected by site
conditions, etc., shall be recorded down in detail.
4.2.4.
For regular impact monitoring,
the sampling frequency of at least once in every six-days, shall be strictly
observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour
TSP monitoring, the sampling frequency of at least three times in every
six-days should be undertaken when the highest dust impact occurs.
Sampling Procedure and
Monitoring Equipment
4.2.5.
High volume samplers (HVSs) in
compliance with the following specifications shall be used for carrying out the
1-hour and 24-hour TSP monitoring:
 -
0.6  1.7 m3 per
minute adjustable flow range;
 -
Equipped with a timing / control
device with +/- 5 minutes accuracy for 24 hours operation;
 -
Installed with elapsed-time meter
with +/- 2 minutes accuracy for 24 hours operation;
 -
Capable of providing a minimum
exposed area of 406 cm2;
 -
Flow control accuracy: +/- 2.5%
deviation over 24-hour sampling period;
 -
Equipped with a shelter to
protect the filter and sampler;
 -
Incorporated with an electronic
mass flow rate controller or other equivalent devices;
 -
Equipped with a flow recorder for
continuous monitoring;
 -
Provided with a peaked roof
inlet;
 -
Incorporated with a manometer;
 -
Able to hold and seal the filter
paper to the sampler housing at horizontal position;
 -
Easily changeable filter; and
 -
Capable of operating continuously
for a 24-hour period.
4.2.6.
Initial calibration of dust
monitoring equipment shall be conducted upon installation and thereafter at
bi-monthly intervals. The transfer standard shall be traceable to the
internationally recognized primary standard and be calibrated annually. The
concern parties such as IEC shall properly document the calibration data for
future reference. All the data should be converted into standard temperature
and pressure condition.
Laboratory Measurement /
Analysis
4.2.7.
A clean laboratory with constant
temperature and humidity control, and equipped with necessary measuring and
conditioning instruments to handle the dust samples collected, shall be
available for sample analysis, and equipment calibration and maintenance. The
laboratory should be HOKLAS accredited.
4.2.8.
Filter paper of size 8 x 10 
shall be labelled before sampling. It shall be a clean filter paper with no
pinholes, and shall be conditioned in a humidity-controlled chamber for over
24-hours and be pre-weighed before use for the sampling.
4.2.9.
After sampling, the filter paper
loaded with dust shall be kept in a clean and tightly sealed plastic bag. The
filter paper shall then be returned to the laboratory for reconditioning in the
humidity controlled chamber followed by accurate weighing by an electronic
balance with readout down to 0.1 mg. The balance shall be regularly calibrated
against a traceable standard.
4.2.10. All the collected samples shall be kept in a good condition for 6 months
before disposal.
4.2.11. Current calibration certificates of equipments are presented in Appendix 4.2.
5.0.1.
The environmental monitoring will
be implemented based on the division of works areas of each designated project
managed under different contracts with separate FEP applied by individual
contractors. Overall layout showing
work areas of various contracts, latest status of work commencement and
monitoring stations is shown in Figure
2.1 and Figure 4.1. The monitoring results are
presented in according to the Individual Contract(s).
5.0.2.
In the reporting month, the
concurrent contracts are as follows:
Contract
no. HY/2009/15  Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
Contract no. HY/2009/17  Central
 Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under
FEP-03/364/2009
Contract no. HY/2009/18  Central
 Wan Chai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A
Contract no. HY/2009/19  Central  
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009
Contract no. HK/2009/01  Wan
Chai Development Phase II  Central  Wan Chai Bypass at Hong Kong Convention
and Exhibition Centre
Contract no. HK/2009/02 - Wan
Chai Development Phase II  Central - Wan Chai Bypass at Wan Chai East
Contract no. HK/2010/06 - Wan Chai Development Phase II  Central
- Wan Chai Bypass over MTR Tsuen Wan Line
5.0.3.
The environment monitoring
schedules for reporting month and coming month are presented in Appendix 5.1.
5.1.1.
Monitoring for report of review
baseline noise level was performed from 11 April 2011 to 8 June 2011. Then the report was submitted on the 20 June
2011, verified by IEC on 18 July 2011 and was approved by ER by January
2012. The new baseline is used for the
noise calculation of this reporting month starting from January 2012.
Contract no. HY/2009/17 –Central  Wan Chai Bypass (CWB) at FEHD
Whitfield Depot  Advanced piling works under FEP-03/364/2009
5.1.2.
The proposed division of noise
monitoring stations for Contract no. HY/2009/17 are summarized in Table
5.1 below:
Table
5.1   Noise Monitoring Stations for Contract no.  /span>HY/2009/17
Station |
Description |
M4b |
Victoria Centre |
5.1.3.
No action or limit level
exceedance was recorded during daytime period in the reporting month. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 5.2. 
Contract no. HY/2009/18  Central  Wan Chai Bypass
(CWB)  Central Interchange under FEP-05/364/2009/A
5.1.4.
Noise monitoring for the Central
Interchange works under contract no. HY/2009/18 was commenced on 22 April
2011.The proposed division of noise monitoring stations for Contract no.
HY/2009/18 are summarized in Table 5.2 below:
Table
5.2   Noise Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
5.1.5.
No action or limit level
exceedance was recorded during daytime period in the reporting
month.
5.1.6.
Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 5.2.
Contract no. HK/2009/01  Wan Chai Development Phase II  Central  Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre  Tunnel Works under
FEP-02/364/2009 and Contract no. HK/2009/02  Wan Chai Development Phase II  
Central  Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.1.7.
The commencement of construction
works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011 and HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed
division of noise monitoring stations are summarized in Table 5.3 below.
Table
5.3   Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.8.
No action or limit level
exceedance was recorded in the reporting month. Noise monitoring results measured in this
reporting period are reviewed and summarized. 
Details of noise monitoring results and graphical presentation can be
referred in Appendix 5.2. 
Contract no. HY/2009/15  Central-Wanchai Bypass  
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
5.1.9.
The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. Noise monitoring was
commenced on 13 July 2011. The proposed divisions of noise monitoring
stations are summarized in Table 5.4 below.
Table 5.4   Noise Monitoring Stations for Contract no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.10. No action or limit level exceedance was recorded in this reporting
month.
5.1.11. Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/19  Central  Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
5.1.12. Noise monitoring for the tunnel works under contract no. HY/2009/19 was
commenced on 24 April 2011. The proposed division of noise monitoring stations
are summarized in Table 5.5 below.
Table
5.5   Noise Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta Secondary School |
5.1.13. No action level and two limit level exceedances were recorded on 7 and
12 June 2012 at M6  HK Baptist Church Henrietta Secondary School in the
reporting month.
5.1.14. Major traffic jam and no major work activities were observed during monitoring,
the exceedances were considered as non-project related.
5.1.15. Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix 5.2. Details of the
Notification of Exceedance can be referred in Appendix 6.2.
5.2.1.
FEHD
Hong Kong Transport Section
Whitefield Depot commenced external wall renovation
from 1 June 2012.
5.2.2.
No construction activity was
conducted during nighttime period (2300 to 0700) in this reporting month.
Contract no.
HY/2009/17 –Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced
piling works under FEP-03/364/2009 and Contract no.
HY/2009/19  Central  Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/A
Table
5.6  Real Time Noise Monitoring Stations for Contract no. HY/2009/17
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
Real time noise monitoring results and graphical presentation during
night time period are for information only.
5.2.4.
No action and
limit level exceedance were recorded in the reporting period. Real time noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of real time noise monitoring results and graphical
presentation can be referred to Appendix 5.4 .
5.2.5.
The proposed division of noise
monitoring stations are summarized in Table 5.7 below. Real time
noise monitoring for major construction works under contract no. HY/2009/19 was
commenced on 24 April 2011.
Table
5.7  Real Time Noise Monitoring
Stations for Contract no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
RTN2 |
North Point |
Oil Street Community Liaison Center |
Real time noise
monitoring results and graphical presentation during night time period are for
information only.
5.2.6.
No action and
limit level exceedance were recorded in the reporting period. Real time noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of real time noise monitoring results and graphical
presentation can be referred to Appendix 5.4 .
5.3.1
Due to extension of site boundary
by contractor of HY/2009/19, location of air monitoring station CMA1b  Oil
Street Community Liaison Centre has been finely adjusted on 21 April 2012.
5.3.2
Due to lack of electricity
supply, the 24-hr TSP monitoring at the following stations were rescheduled:
CMA1b: from 6 June 2012 to 7 June 2012
CMA5a: from 6 June 2012 to 7 June 2012
CMA2a: from 18 June 2012 to 19 June 2012
5.3.3
The data for the rescheduled air
monitoring for CMA1b, dated 30 April 2012, will be presented in the next
monthly report (May 2012).
Contract no. HY/2009/17 –Central  Wan Chai Bypass (CWB) at FEHD
Whitfield Depot  Advanced piling works under FEP-03/364/2009
5.3.4
The proposed division of air
monitoring stations are summarized in Table 5.8 below. Air monitoring for
the piling works under contract no. HY/2009/17 was commenced on 8 October 2010.
Table
5.8   Air Monitoring Station for Contract no. HY/2009/17
Station |
Description |
CMA1b |
Oil Street
Community Liaison Centre |
CMA2a |
Causeway Bay Community Centre |
5.3.5
No exceedance was recorded in the
reporting month. Air quality monitoring results measured in this reporting
period are reviewed and summarized. 
Details of air monitoring results and graphical presentation can be
referred in Appendix 5.3. 
Contract no. HY/2009/18  Central  Wan Chai
Bypass (CWB)  Central Interchange under FEP-05/364/2009/A
5.3.6
Air monitoring for the Central
Interchange works under contract no. HY/2009/18 was commenced on 21 April
2011.The proposed division of air monitoring stations are summarized in Table
5.9 below.
Table
5.9   Air Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of Podium) |
MA1w |
International Finance Centre (Western End of Podium) |
5.3.7
No exceedance was recorded in the
reporting month. Air quality monitoring results measured in this reporting
period are reviewed and summarized. 
Details of air monitoring results and graphical presentation can be
referred in Appendix 5.3. 
Contract no. HK/2009/01  Wan Chai Development Phase II  Central  Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre  Tunnel Works under
FEP-02/364/2009
5.3.8
The commencement of construction
works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011. Air quality monitoring was commenced on 25 August 2011. The proposed
division of air monitoring stations are summarized in Table 5.10 below.
Table
5.10 Air Monitoring Station for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to Pedestrian Plaza |
5.3.9
No exceedance was recorded in the
reporting month. Air quality monitoring results measured in this reporting
period are reviewed and summarized. 
Details of air monitoring results and graphical presentation can be
referred in Appendix 5.3. 
Contract no. HK/2009/02  Wan Chai Development Phase II  Central  Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.3.10
The commencement of construction
works for HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed
division of air monitoring stations are summarized in Table 5.11 below.
Table
5.11 Air Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
5.3.11
No exceedance was recorded in the
reporting month. Air quality monitoring results measured in this reporting
period are reviewed and summarized. 
Details of air monitoring results and graphical presentation can be referred
in Appendix 5.3. 
Contract no. HY/2009/15  Central-Wanchai Bypass  
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
5.3.12
The commencement of construction
works for Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011.
Air quality monitoring was commenced on 14 July 2011. The proposed division of air monitoring
stations are summarized in Table 5.12 below.
Table 5.12 Air Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.3.13
No exceedance was recorded in the
reporting month. Air quality monitoring results measured in this reporting
period are reviewed and summarized. 
Details of air monitoring results and graphical presentation can be referred
in Appendix 5.3. 
Contract no. HY/2009/19  Central  Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
5.3.14
The proposed division of air
monitoring stations are summarized in Table 5.13 below. Air monitoring for
the tunnel works under contract no. HY/2009/19 was commenced on 26 April 2011.
Table
5.13 Air Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Oil St Community Liaison Centre |
CMA2a |
Causeway Bay Community Centre |
5.3.15
No exceedance was recorded in the
reporting month. Air quality monitoring results measured in this reporting
period are reviewed and summarized. 
Details of air monitoring results and graphical presentation can be referred
in Appendix 5.3.
Contract no. HY/2009/17 –Central  Wan Chai Bypass (CWB) at FEHD
Whitfield Depot  Advanced piling works under FEP-03/364/2009
5.4.1.
No Inert and non-inert C&D
wastes were disposed in the reporting month. Details of the waste flow table
are summarized in Table 5.14
Table 5.14 Details of Waste Disposal
for Contract no. HY/2009/17
Waste Type |
Quantity this month, m3 |
Cumulative Quantity-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
N/A |
||
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
N/A |
N/A |
N/A |
Contract nos. HK/2009/01  Wan Chai Development
Phase II  Central  Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre  Tunnel Works under FEP-02/364/2009
5.4.2.
Inert and non-inert C&D wastes
were disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.15.
Table
5.15 Details of Waste Disposal for Contract no. HK/2009/01
Waste Type |
|||
Inert C&D materials disposed |
113.77 |
19,285.22 |
TKO137, TM38 |
Inert C&D materials recycled |
NIL |
389.96 |
N/A |
Non-inert C&D materials disposed |
87.08 |
798 |
SENT Landfill |
Non-inert C&D materials recycled |
10,776 |
147,100 |
N/A |
Chemical waste disposed |
380 |
6,510 |
N/A |
Contract no. HK/2009/02  Wan Chai Development
Phase II  Central  Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
5.4.3.
Inert C&D & non-inert
C&D wastes were disposed of in this reporting month. Details of the waste
flow table are summarized in Table 5.16.
Table 5.16 Details of Waste Disposal
for Contract no. HK/2009/02
Inert C&D materials disposed |
19,376 |
159,506 |
TKO137, TM 38 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
39 |
323 |
SENT Landfill |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed (kg) |
NIL |
4,186 |
N/A |
Remarks Contractor clarified and updated waste flow
table for the reporting month of April
Contract no. HY/2009/18  Central  Wan Chai Bypass
(CWB)  Central Interchange under FEP-05/364/2009/A
5.4.4.
Inert C&D and non-inert
C&D waste was disposed of in this reporting month. Details of the waste
flow table are summarized in Table 5.17.
Table 5.17 Details of Waste Disposal
for Contract no. HY/2009/18
Inert C&D materials disposed |
3,267 |
35,202 |
T.K.O. 137, TM 38 |
Inert C&D materials recycled |
1,183 |
9,146 |
N/A |
Non-inert C&D materials disposed |
37 |
348 |
SENT Landfill |
Non-inert C&D materials recycled (tonnes) |
0.3 |
40.6 |
N/A |
Chemical waste disposed (kg) |
760 |
2,985 |
N/A |
Remarks Contractor clarified and updated waste flow
table for the reporting month of April
Contract no. HY/2009/15  Central-Wanchai Bypass  
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
5.4.5.
Inert & Non-inert C&D wastes were disposed of in
this reporting month. Details of the waste flow table
are summarized in Table 5.18.
Table 5.18 Details of Waste Disposal
for Contract no. HY/2009/15
Inert C&D materials disposed |
307.8 |
141,959.5 |
Tuen Mun Area 38 |
|
27,381.7 |
124,166.2 |
TKO137 FB |
Inert C&D materials recycled |
NIL |
415.9 |
HY/2009/11 ex-PCWA TS4 |
Non-inert C&D materials disposed |
84.9 |
315.6 |
SENT Landfill |
Non-inert C&D materials recycled |
6.6 |
376.5 |
Xun
Xiang Metalware Skylight
Recycle (paper) |
Chemical waste disposed |
1,800 |
10,000 |
Dunwell
Group |
Remarks Contractor clarified and
updated waste flow table for the reporting month of January and the cumulative
sum of inert C&D materials has been updated in the March to May 2012
Quarterly Report.
Contract no. HY/2009/19  Central  
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
5.4.6.
Inert and Non-inert C&D wastes
were disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.19.
Table 5.19 Details of Waste Disposal
for Contract no. HY/2009/19
Inert C&D materials disposed |
21,064.78 |
106,683.22 |
N/A |
Inert C&D materials recycled |
0 |
1,801.91 |
N/A |
Non-inert C&D materials disposed |
22.86 |
484.25 |
SENT Landfill |
Non-inert C&D materials recycled |
0.11 |
42.81 |
N/A |
Chemical waste disposed |
0 |
4.13 |
N/A |
 /span>Remarks Contractor clarified and
updated waste flow table for the reporting month of April
Contract no.
HK/2010/06 Wan Chai
Development Phase II - Central-Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
5.4.7.
No inert and Non-inert C&D
wastes were disposed of in this reporting month. Details of the waste flow
table are summarized in Table 5.20.
Table 5.20 Details of Waste Disposal
for Contract no. HK/2010/06
Inert C&D materials disposed |
NIL |
NIL |
TM38 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
Recyclers |
Chemical waste disposed |
NIL |
NIL |
N/A |
 /span>
6.0.1.
The Event Action Plan for
construction noise, air qualities are presented in Appendix 6.1.
Contract no. HY/2009/17 –Central  Wan Chai Bypass (CWB) at FEHD
Whitfield Depot  Advanced piling works under FEP-03/364/2009
6.1.1.
No exceedance
was recorded in the reporting month.
Contract no.
HY/2009/18  Central  Wan Chai Bypass (CWB)  Central Interchange under
FEP-05/364/2009/A
6.1.2.
No exceedance
was recorded in the reporting month.
Contract no. HK/2009/01  Wan Chai Development
Phase II  Central  Wan Chai Bypass at Hong Kong Convention Exhibition Centre
 Tunnel Works under FEP-02/364/2009
6.1.3.
No exceedance
was recorded in the reporting month.
Contract no. HK/2009/02  Wan Chai
Development Phase II  Central  Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
6.1.4.
No exceedance
was recorded in the reporting month.
Contract no. HY/2009/15  Central-Wanchai Bypass  Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
6.1.5.
No exceedance
was recorded in the reporting month.
Contract no. HY/2009/19  Central  Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
6.1.6.
No action
level and two limit level exceedances were recorded at M6  HK Baptist Church Henrietta
Secondary School on 7 and 12 June 2012 in the reporting month.
 /span>Investigation found that major traffic
noise was contributed in the noise monitoring and not related to
the Project.
Real Time Noise Monitoring
Contract no. HY/2009/17  Central  Wan Chai Bypass (CWB) at FEHD
Whitfield Depot  Advanced piling works under FEP-03/364/2009
6.1.7.
No exceednace
was recorded in the reporting month.
Contract no. HY/2009/19  Central  
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
6.1.8.
No exceednace
was recorded in the reporting month.
Contract no.
HY/2009/17  Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced
piling works under FEP-03/364/2009
6.2.1.
No exceedance
was recorded in the reporting month.
Contract no.
HY/2009/18  Central  Wan Chai Bypass (CWB)  Central Interchange under
FEP-05/364/2009/A
6.2.2.
No exceednace
was recorded in the reporting month.
Contract no.
HK/2009/01  Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre  Tunnel Works under FEP-02/364/2009
6.2.3.
No exceednace
was recorded in the reporting month.
Contract no.
HK/2009/02  Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
6.2.4.
No exceednace
was recorded in the reporting month.
Contract no. HY/2009/15  Central-Wanchai Bypass  
Tunnel (Causeway Bay Typhoon Shelter Section) FEP-06/364/2009/A
6.2.5.
No exceednace
was recorded in the reporting month.
Contract no. HY/2009/19  Central  
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
6.2.1
No exceednace
was recorded in the reporting month.
6.3.1.
There was no non-compliance from
the site audits in the reporting period. The observations and recommendations
made in each individual site audit session were presented in Section 8.
6.3.2.
No project-related non-compliance
from monitoring was recorded in the reporting month.
7.0.1.
According
to Condition 3.4 of the EP-364/2009/A, this section addresses the relevant
cumulative construction impact due to the concurrent activities of the current
projects including the Central Reclamation Phase III (CRIII), Wan Chai
Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern
Corridor Link projects (IECL) and Wan Chai Development Phase II  Central  Wan
Chai Bypass at Wan Chai East (CWB Tunnel).
7.0.2.
According
to the Monthly EM&A report (May 2012) of Central Reclamation Phase III
(CRIII), filling works, building construction works and pipe works were
performed in the May 2012 reporting month. The water quality monitoring was
completed in October 2011 and no exceedance was recorded for air and noise
monitoring. It can be concluded that cumulative
construction impact due to the concurrent activities of the current projects with
the Central Reclamation Phase III (CRIII) was insignificant.
7.0.3.
According
to the construction programme of Central Reclamation Phase III,
Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern
Corridor Link projects, the major construction activity under Central Reclamation Phase III were
general filling works in IRAE; Wan Chai Development Phase II was
marine works at HKCEC areas, cross-harbour Watermains, Fresh Watermains,
Cooling Watermains and Salt Watermains Installations, tunnel works at Wan Chai
East, diaphragm wall construction at TS4; dredging at TS2; deep excavation at
TS1 and TPCWAE TCBR1W. Advanced piling works at FEHD Whitfield Depot, Central
Interchange, and diaphragm wall construction at North Point area. The major
environmental impact was water quality impact at Causeway Bay and Wan Chai.
Land-based construction activity were Diaphragm wall construction at TS4, Diaphragm
wall construction at TS1 and TPCWAE TCBR1W, piling works at FEHD
Whitfield Depot, Diaphragm wall at Central and North Point and tunnel works at
Wan Chai East in the reporting month.
7.0.4.
The major
environmental impacts generated from CRIII advanced
piling works at FEHD Whitfield Depot were undertaken and Diaphragm wall
construction at Central and tunnel works at Wan Chai East, IECL and Causeway
Bay typhoon shelter in the reporting month. No significant air impact was
anticipated in the reporting month. Besides, no Project-related exceedance was
recorded during the environmental monitoring events in the reporting month. Thus, it is evaluated that the cumulative
construction impact from the concurrent projects including Wan Chai Development
Phase II and Central Reclamation Phase III was
insignificant.
8.0.1.
During this reporting month,
weekly environmental site audits were conducted for Contracts no. HY/2009/15,
HY/2009/17, HY/2009/18, HY/2009/19, HK/2009/01, HK/2009/02 and HK/2010/06. No
non-conformance was identified during the site audits.
8.0.2.
Five site inspections for
Contract no. HY/2009/15 was carried out during this reporting period. The
results of these inspections and outcomes are summarized in Table
8.1.
Table 8.1  Summary of Environmental Inspections for Contract no. HY/2009/15
Date |
Item |
Observations |
Action taken by
Contractor |
Outcome |
29-May-12 |
120529_01 |
Oil should
be removed as chemical waste and steps should be taken to avoid leakage into
sea |
Oil was
removed. |
Completion
as observed on 5-Jun-12 |
5-Jun-12 |
120605_01 |
Cares
should be taken to avoid mud getting out of site area and muddy trial should
be cleared. (Gate of TS4, outside POC) |
Muddy trail
was cleared. |
Completion
as observed on 12-Jun-12 |
12-Jun-12 |
120612_01 |
Protection
around public gully should be provided to prevent runoff. (Outside POC) |
Sandbags
were provided around the public gullies. |
Completion
as observed on 19-Jun-12 |
12-Jun-12 |
120612_02 |
Cement bags
should be covered with tarpaulin sheet (Barge at TPCWAE) |
Cement bags
were covered with tarpaulin sheet. |
Completion
as observed on 19-Jun-12 |
12-Jun-12 |
120612_03 |
Floating
refuse should be removed regularly (TS1, by sedimentation tank) |
Floating
refuse were collected |
Completion
as observed on 19-Jun-12 |
19-Jun-12 |
120619_01 |
Muddy water
was observed to be pumping into sea. 
Actions should be taken to avoid improper discharge. |
Pipe
discharging muddy water was removed from discharge point and placed into
pumping well. |
Completion
as observed on 26-Jun-12 |
26-Jun-12 |
120626_01 |
Handheld
breakers should have valid NEL displayed while in use (TS1) |
Handheld breakers
were removed offsite. |
Completion as
observed on 3-Jul-12 |
26-Jun-12 |
120626_02 |
Cement
mixing should be performed in sheltered area (TS1) |
Cement mixing
activities were removed from open area. |
Completion as
observed on 3-Jul-12 |
26-Jun-12 |
120626_03 |
Effective
wheel wash area should be provided so that wheels are washed and do not carry
mud off site. (Gate of TS4/ME4) |
Mud was cleared
from wheel wash area. |
Completion as
observed on 3-Jul-12 |
26-Jun-12 |
120626_04 |
Proper
labeling and adequate drip trays should be provided for drums |
Drums were removed
site. |
Completion as
observed on 3-Jul-12 |
8.0.3.
Four site inspections for
Contract no. HY/2009/18 was carried out during this reporting period. No
observation was found in the reporting month.
8.0.4.
 /span>Four site inspections for Contract no.
HY/2009/19 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table
8.2.
Table 8.2  Summary of Environmental
Inspections for Contract no. HY/2009/19
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
120530_01 |
30-May-12 |
Adequate
drip tray should be provided for oil drums (Portion III and all platforms) |
Drip trays
were provided for oil drums. |
Completion
as observed on 6-Jun-12 |
120530_02 |
30-May-12 |
Hole at
drip tray should be plugged and oil plus contaminated soil should be removed
as chemical waste (portion III) |
Hole at
drip tray was filled. |
Completion
as observed on 13-Jun-12 |
120530_03 |
30-May-12 |
Proper
labeling should be given to chemical/oil drums and adequate storage area
should be provided (platforms, portion III) |
MSDS was
provided showing the drums were containing material that does not need
labeling, drip tray was also provided. |
Completion
as observed on 13-Jun-12 |
120606_01 |
6-Jun-12 |
Adequate
drip trays should be provided for oil drums (Portion III) |
Hole at
drip tray was filled. |
Completion
as observed on 13-Jun-12 |
120606_02 |
6-Jun-12 |
Gaps and
holes on platforms should be protected to avoid runoff into sea. |
Sandbags
were used to fill the holes and gaps were filled. |
Completion
as observed on 13-Jun-12 |
120613_01 |
13-Jun-12 |
Tree protection zone should be free of construction activities
(Portion III). |
Tree was transplanted on 19-Jun-12. |
Completion as observed on 20-Jun-12 |
120613_02 |
13-Jun-12 |
Cement bags should be covered with tarpaulin sheet (Portion
III). |
Cement bags were covered with plastic sheets. |
Completion as observed on 20-Jun-12 |
120620_01 |
20-Jun-12 |
Adequate drip trays should be provided for oil drums. (Portion
III) |
Oil drums were removed from site. |
Completion as observed on 27-Jun-12 |
120627_01 |
27-Jun-12 |
Proper labelling and adequate drip tray should be provided for
drums (Box culvert T1 at Watson Road) |
Drum was removed from site. |
Completion as observed on 4-Jul-12 |
120627_02 |
27-Jun-12 |
Effective noise blankets should be erected on working platforms
(all platforms) |
No actions were performed |
Follow-up observed on 4-Jul-12 |
8.0.5.
Five site inspections for
Contract no. HK/2009/01 was carried out during this reporting period. The
results of these inspections and outcomes are summarized in Table
8.3.
Table 8.3  Summary of Environmental
Inspections for Contract no. HK/2009/01
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
120530_01 |
30-May-12 |
The muddy water was observed on the roadside from wheel washing
facilities which should be cleaned (Water Channel) |
Muddy water was removed from roadside. |
Completion as observed on 6-June-12 |
120606_01 |
6-Jun-12 |
The discharge should be treated before discharge to the manhole
(Opposite to Grand Hyatt) |
Discharge at manhole was stopped and diverted to treatment facilities. |
Completion as observed on 13-June-12 |
120606_01 |
6-Jun-12 |
Drip trays should be provided for oil drums (Water Channel) |
Drip tray was provided for oil drums. |
Completion as observed on 13-June-12 |
120606_01 |
6-Jun-12 |
The muddy water was observed outside the silt curtain, which should be maintained properly to prevent the leakage of
the muddy water. (Water Channel) |
Better maintenance of silt curtain. |
Completion as observed on 13-June-12 |
120613_01 |
13-Jun-12 |
The spillage of water from sedimentation tank was observed which
should be repaired or
replaced by new one (Opposite to site office) |
Sedimentation tank was repaired. |
Completion as observed on 20-June-12 |
120613_02 |
13-Jun-12 |
The leakage of fuel oil was observed on the floor which should
be removed and disposed as chemical waste
(Opposite to site office) |
Oil leakage was removed. |
Completion as observed on 20-June-12 |
120613_03 |
13-Jun-12 |
The muddy water was discharging from sedimentation tank, the silt inside the tank should be cleaned regularly (TST) |
Silt was cleared from sedimentation
tank. |
Completion as observed on 20-June-12 |
120613_04 |
13-Jun-12 |
The muddy water was observed outside the site area which should
be removed (VIP area) |
Muddy water was removed. |
Completion as observed on 20-June-12 |
120620_01 |
20-Jun-12 |
The bentonite bags should be covered by tarpaulin sheet
completely (Water Channel) |
Bentonite bags were covered. |
Completion as observed on 27-June-12 |
120620_02 |
20-Jun-12 |
The oil stain was observed on ground which should be removed and
disposed as chemical waste (B2,
opposite to site office) |
Oil stain was removed. |
Completion as observed on 27-June-12 |
120627_01 |
27-Jun-12 |
The silt curtain should be provided for rockfilling in HKCEC
channel. (Water Channel) |
Silt curtain was provided |
Completion as observed on
4-Jul-12 |
8.0.6.
Four site inspections for
Contract no. HK/2009/02 was carried out during this reporting period. The
results of these inspections and outcomes are summarized in Table
8.4.
Table 8.4   Summary of Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
120531_01 |
31-May-12 |
Drip tray should be provided for oil drum (small ex-pet garden) |
Drip tray was provided for oil drum. |
Completion
as observed on 7-June-12 |
120531_02 |
31-May-12 |
The bentonite bags should be covered by tarpaulin sheet (Gate 2) |
Bentonite bags were covered by
tarpaulin sheet. |
Completion
as observed on 7-June-12 |
120607_01 |
7-Jun-12 |
Drip trays should be provided for oil drums and the drain hole
should be plugged properly. (Harbour Road, WCR1) |
Drip tray was provided for oil drum
and all drain holes were plugged. |
Completion
as observed on 14-June-12 |
120607_02 |
7-Jun-12 |
The leakage of water from the pipe to the roadside was observed
which should be removed and the pipe should be repaired. (Harbour Road) |
Pipe was repaired and water leakage was removed. |
Completion
as observed on 14-June-12 |
120614_01 |
14-Jun-12 |
The muddy water was observed from the site boundary on the road
which should be removed (small ex-pet garden) |
Muddy water was removed from road. |
Completion
as observed on 20-June-12 |
120614_02 |
14-Jun-12 |
The floating debris should be cleaned regularly (small ex-pet
garden) |
Floating debris was collected. |
Completion
as observed on 20-June-12 |
120614_03 |
14-Jun-12 |
The stagnant water was observed within the site area which
should be removed (WCR1, WSD pumping station) |
Stagnant water was removed. |
Completion
as observed on 20-June-12 |
120614_04 |
14-Jun-12 |
The muddy water from the excavation pit was discharged directly
which should not be allowed and should be treated prior to discharge. (WCR1) |
Muddy water was diverted to treatment before discharge. |
Completion
as observed on 20-June-12 |
120620_01 |
20-Jun-12 |
The oil stain was observed on the floor which should be removed
and disposed as chemical waste
(WCR1) |
Oil stain was removed. |
Completion
as observed on 28-June-12 |
8.0.7.
Five site inspections for
Contract no. HY/2009/17 were carried out during this reporting period. No
observation was found in the reporting month.
8.0.8.
Five site inspections for
Contract no. HK/2010/06 was carried out during this reporting period. The
results of these inspections and outcomes are summarized in Table
8.5.
Table 8.5   Summary of Environmental Inspections for Contract no. HK/2010/06
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
120604_01 |
4-Jun-12 |
The equipments and materials in the drip tray should be removed
and the accumulated water should be removed and disposed as chemical waste
(2e) |
Equipments, materials and water were
removed from drip tray. |
Completion
as observed on 11-Jun-12 |
120611_01 |
11-Jun-12 |
The oil stain was
observed on the platform which should be removed and disposed as chemical
waste (2e and 2w) |
Oil leakage was removed. |
Completion
as observed on 21-Jun-12 |
120611_02 |
11-Jun-12 |
The stagnant water and silt accumulated on the U-channel should be removed (2w) |
Stagnant water and silt was removed. |
Completion
as observed on 21-Jun-12 |
120625_01 |
25-Jun-12 |
The oil stains was observed on the platform which should be
removed and disposed as chemical
waste (Eastern Platform) |
Oil stain was removed as chemical waste. |
Completion as observed on 3-Jul-12 |
9.0.1.
No environmental
complaint was received in the reporting period.
9.0.2.
The details of
cumulative complaint log and updated summary of
complaints are presented in Appendix 9.1
9.0.3.
Cumulative statistic on
complaints and successful prosecutions are summarized in Table 9.1 and Table
9.2 respectively.
Table 9.1  Cumulative Statistics
on Complaints
Reporting Period |
No. of Complaints |
June 12 |
0 |
Sep 10 to May 12 |
20 |
Total |
20 |
Table 9.2  Cumulative Statistics on Successful
Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1. The EM&A programme was carried out in accordance with the EM&A
Manual requirements, minor alterations to the programme proposed were made in
response to changing circumstances.
10.0.2. The scheduled construction activities and the recommended mitigation
measures for the coming month are listed in Table 10.1. The
construction programmes of individual contracts are provided in Appendix 10.1.
Table 10.1   Summary of Key Construction Activities of
Individual Contract(s) to be commenced in Coming Reporting Month
Contract No. |
Key Construction Works |
Recommended Mitigation Measures |
HY/2009/15 |
 -
Diaphragm
wall construction works at TS4  -
ELS works
at TPCWAE  -
Cut and
cover tunnel construction at TPCWAE  -
Mined
tunnel preparation works at TPCWAE and Hung Hing Road |
 -
Watering
any dust generating activities  -
Checking
all drip trays frequently and clear any stagnant water and mud inside it.  -
Noise
control measures shall be provided during restricted hours. |
HY/2009/17 |
 -
ELS works for
basement construction for pile cap construction. |
 -
Noise
barrier shall be implemented; and  -
Watering
any dust generating activities |
HY/2009/18 |
 -
Trial pit  -
Instrumentation
and monitoring works  -
Drainage
works  -
Site
investigation and pre-drilling works  -
D-wall construction  -
Sheet
piling  -
Tree
Transplantation  -
Earthworks  -
Preparation
works in existing tunnel  -
Approach
ramp (trough) structure works  -
Top down
slab  -
Road works  -
Tunnel
works  -
Excavation
and Lateral Support  -
Pipe-pile
works  -
Cooling
main bridge construction  -
Bridge A
construction |
 -
Noise
barrier shall be implemented; and  -
Noise level
shall be controlled by reducing piling rate and no. of plants working in
parallel.  -
Dust
control during dust generating works  -
Provide
protection works to ensure no runoff out of site area or direct discharge
into public drainage system. |
HY2009/19 |
 -
Road works
at Watson Road  -
Laying od
1500f drainage pipe  -
Fabrication
of bored piling platform  -
Bored
piling (Land)  -
Ground
contamination assessment  -
Pre-drilling
works for bored pile and Diaphragm wall  -
D-wall Construction
(North & South Section)  -
Guide wall
construction for D-wall / Barette at North side  -
Construction
works for Box Culvert T  -
Construct
ion of socket-H pile for Marine works  -
Construction
of pre-bored H-pile works for Culvert U  -
Construction
of 1500 drainage along D-wall  -
Construction
of pile cap |
 -
Noise level
shall be controlled by reducing the pilling operation rate.  -
Noise
barrier shall be implemented.  -
Dust
control during dust generating works  -
Provide
protection works and adequate drainage system to ensure no direct discharge
into public drainage system or the sea. |
HK2009/01 |
 -
Diaphragm
wall construction for CWB tunneling works at Stage2  -
Waterproofing
works for CWB top slab  -
Excavation
and installation of shoring system for construction of exhaust dust  -
Construction
of exhaust duct structure (Bay1)  -
Construction
of exhaust duct structure (Bay2)  -
Load test
on SCL pre-bored H-piles works  -
Excavation
for construction of SCL top slab  -
Construction
of SCL top slab (Bay 3)  -
Construction
of SCL top slab (Bay1 and Bay 2) |
 -
Noise level
shall be controlled by reducing no. of plants working in parallel.  -
Well
maintained enclosures for grouting and bentonite mixing plants.  -
Provide
protection works and adequate drainage system to ensure no direct discharge
into public drainage system or the sea. |
HK/2009/02 |
 -
Bored
piling, breaking concrete slab and excavation of trial pit at tunnel portion
3 & 4.  -
Deep
excavation and strut installation works below -9.8mPD for western tunnel
portion and below +9.0mPD for eastern tunnel portion. |
 -
Well
maintain the enclosures for grouting and bentonite mixing plants.  -
Dust
control during dust generating works  -
Provide
protection works to ensure no runoff out of site area or direct discharge
into public drainage system. |
HK/2010/06 |
 -
Construction
of Pre-cast Unit in China |
 -
Air
pollution control during transportation |
10.0.3. The construction works of Contract no. 04/HY/2006  Reconstruction of
Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A was completed, and the FEP
was surrendered by the Contractor on 11 February 2011.